8-KRegulation FDOther EventsExhibits & Filings

DOMINION ENERGY, INC 8-K Report, Regulation FD Disclosure (Dec 23, 2025)

Filed December 23, 2025For Securities:D

Summary

Dominion Energy, Inc. (D) has filed an 8-K report disclosing a significant development concerning its Coastal Virginia Offshore Wind (CVOW) project. The U.S. Department of the Interior's Bureau of Ocean Energy Management (BOEM) has issued a Director's Order suspending all work on the project for 90 days, effective immediately as of December 22, 2025. This suspension impacts OSW Project LLC, in which Virginia Electric and Power Company, a Dominion Energy subsidiary, holds a 50% membership interest.

Key Highlights

  • 1BOEM has issued a 90-day suspension of work order for the Coastal Virginia Offshore Wind (CVOW) project.
  • 2The suspension is effective immediately as of December 22, 2025.
  • 3Dominion Energy's subsidiary, Virginia Electric and Power Company, holds a 50% stake in OSW Project LLC, the entity affected by the order.
  • 4The company issued a press release on December 22, 2025, to communicate this development.
  • 5The information is being furnished under Regulation FD and other-events disclosures, not considered 'filed' for certain liabilities.