This 8-K filing from Exelon Corporation (EXC) on June 6, 2003, addresses a critical issue concerning its indirect subsidiary, Exelon Boston Generating, LLC (EBG), and its $1.1 billion credit facility (EBG Facility). The facility, used to finance the construction of the Mystic 8 and 9 and Fore River generating units, has a Project Completion deadline of June 12, 2003, which EBG anticipates it will not meet. This failure to meet the deadline triggers significant potential consequences under the EBG Facility, including the possibility of lenders declaring all outstanding amounts due, terminating interest rate swaps, foreclosing on assets, or requiring cash usage to reduce debt.

Key Highlights

  • 1Exelon subsidiary EBG is expected to miss the June 12, 2003 "Project Completion" deadline for the Mystic 8/9 and Fore River generating units, impacting a $1.1 billion credit facility.
  • 2Failure to meet the deadline triggers potential default clauses in the EBG Facility, including acceleration of debt, termination of swaps, and foreclosure.
  • 3The EBG Facility is non-recourse to Exelon Corporation and Exelon Generation Company, LLC; an EBG default does not impact other Exelon debt.
  • 4EBG has requested an amendment to extend the "Project Completion" deadline to July 11, 2003, subject to unanimous lender approval (19 lenders).
  • 5EBG does not expect to meet even the extended deadline and acknowledges uncertainty regarding lender approval and potential future negotiations or actions.
  • 6The company is evaluating all options regarding the anticipated failure to meet project completion milestones.