Summary
Summary of the 8-K filed July 23, 2026. Cited figures are marked; the original filing is the authoritative source.
Freeport-McMoRan (FCX) reported second-quarter 2026 net income attributable to common stock of $984 milliona ($0.68 per diluted share), or $1.1 billion ($0.74 per share) on an adjusted basis after $96 million of after-tax net charges, mostly tied to idle facility and restoration costs from PTFI's September 2025 mud rush incident.
Consolidated copper sales were 710 million pounds, above the April estimate of 690 million, while gold sales of 123 thousand ounces came in below the 140 thousand estimate. Average realized prices were $6.17b/lb copper and $4,520/oz gold, and unit net cash costs were $1.97/lb, favorable to the April estimate of $2.24/lb. Operating cash flow was $2.0 billion after $0.6 billion of working capital uses, and this quarter included $0.7 billion of PTFI insurance proceeds.
The Grasberg Block Cave ramp-up is described as on schedule, with planned operating rates achieved in Q2 and PTFI production expected at roughly 65% in 2H26, 80% by mid-2027 and near full capacity by year-end 2027. Full-year 2026 guidance calls for 3.1 billion pounds of copper sales, 650 thousand ounces of gold, and unit net cash costs of $1.90c/lb, with capex of $4.3 billion, of which $3.0 billion is for major mining projects. Operating cash flow is expected to be about $8.3 billion, assuming $6.00/lb copper for the second half.
Net debt excluding PTFI downstream debt was $2.1 billiond at June 30, and FCX repurchased shares and raised its Cerro Verde stake to 55.66%. The company also advanced its growth pipeline. A potential Bagdad expansion, which would add 200 to 250 million pounds of copper per year, now carries an estimated capex about 30% above the 2023 estimate of $3.5 billion, and a potential investment decision is targeted for 2H26.
An El Abra expansion, with environmental impact study submitted in March 2026, could add over 700 million pounds per year. The Indonesian long-term operating rights MOU and the IUPK extension application were submitted, though the license process is not complete.
02—Key points
Key Highlights
- Q2 2026 net income attributable to common stock was $984M ($0.68/share), versus $772M ($0.53/share) in Q2 2025; adjusted net income was $1.1B ($0.74/share) after $96M of after-tax charges.
- Copper sales of 710M lbs beat the April estimate of 690M lbs, while unit net cash costs of $1.97/lb beat the $2.24/lb estimate, though sales were down from 1,016M lbs a year earlier due to reduced PTFI volumes during the ramp-up.
- Q2 realized copper price was $6.17/lb (vs. $4.54 a year ago), and 1H26 operating income was $4.1B versus $3.7B in 1H25, aided by a $699M PTFI insurance settlement gain.
- Full-year 2026 outlook: 3.1B lbs copper, 650k oz gold, 93M lbs moly, unit net cash costs of $1.90/lb, operating cash flow of ~$8.3B, and capex of ~$4.3B (including $1.6B of discretionary projects).
- Grasberg Block Cave ramp-up is on schedule: ~65% of capacity expected in 2H26, ~80% by mid-2027, and near full capacity by year-end 2027. Idle facility and restoration costs were $284M in Q2.
- Balance sheet remains solid: consolidated cash of $4.1B, net debt of $2.1B excluding $3.2B of PTFI downstream debt (within the $3–4B target), and $3.0B of undrawn FCX revolver availability.
- Capital returns continued with a $0.15/share dividend declared, $110M of Q2 buybacks, and a $0.5B Cerro Verde stake purchase increment; the company has repurchased $2.2B of its $5.0B authorization to date.
03—Questions
Frequently Asked Questions
Why did FCX's Q2 2026 copper sales decline year over year?
Consolidated copper sales fell to 710M lbs from 1,016M lbs in Q2 2025, mainly because PTFI operated at lower rates during the phased ramp-up of the Grasberg Block Cave mine after the September 2025 mud rush incident. South America sales also declined to 245M lbs from 265M lbs, reflecting lower leach production and lower-grade stockpile ore. The company expects copper sales to total about 3.1B lbs in 2026, with the Q3 estimate at 750M lbs.
How much of the Q2 earnings were affected by one-time or non-recurring items?
After-tax net charges totaled $96M ($0.06/share) in Q2 2026, primarily for idle facility and restoration costs tied to the PTFI incident. Adjusted net income of $1.1B ($0.74/share) excludes these charges. Separately, the first half of 2026 included a $699M pre-tax gain on the PTFI insurance settlement, although $0.7B of the related proceeds was collected in Q2 and is not expected to recur.
What is the outlook for the Grasberg mine and when could production normalize?
PTFI expects production to reach about 65% of capacity in 2H26, about 80% by mid-2027, and near full capacity by year-end 2027. The Production Block 1S restart is targeted for mid-2027. Management noted that PTFI's downstream smelting facilities may continue to create variability between production and sales until they reach normalized operating rates.
Is FCX's balance sheet and shareholder return policy under pressure from the growth capex?
FCX's net debt excluding PTFI downstream debt was $2.1B at June 30, 2026, well inside its $3–4B target. The company's financial policy directs up to 50% of available cash flow to shareholders, and it has returned $6.3B since mid-2021. Capex of about $4.3B in 2026, including $1.6B of discretionary spending, is substantial, so cash generation at the 2026 price assumptions will be important to sustaining both growth investment and returns.
What are the key risks to the growth projects highlighted in the filing?
The Bagdad expansion's capital cost estimate has risen about 30% from the 2023 estimate of $3.5B, and it still needs a final investment decision in 2H26, with economics supported at about $4.00/lb copper. The El Abra expansion requires environmental permitting in Chile, and the Indonesia license extension beyond 2041 depends on completing a formal IUPK process with the government. Any delays or further cost increases could affect the timing and returns on these projects.