8-KOther Events

LOCKHEED MARTIN CORP 8-K Report, Corporate Update (Sep 6, 2023)

Filed September 6, 2023For Securities:LMT

Summary

Lockheed Martin Corporation (LMT) announced an update regarding its Technology Refresh 3 (TR-3) program for the F-35 fighter jet. The company now anticipates delivering the first TR-3 configured jet between April and June 2024, a shift from previous projections. Despite this delay, LMT expects to meet its 2023 delivery target of 97 aircraft, all in the TR-2 configuration, and currently forecasts no impact on its 2023 financial outlook. The production rate for F-35s remains strong at 156 aircraft per year, a pace the company intends to maintain while working through TR-3 software development and hardware procurement from suppliers.

Key Highlights

  • 1First TR-3 configured F-35 jet delivery now expected between April and June 2024.
  • 22023 F-35 delivery target of 97 aircraft remains achievable, all in TR-2 configuration.
  • 3No anticipated impact on the 2023 financial outlook due to TR-3 schedule update.
  • 4F-35 production rate maintained at 156 aircraft per year.
  • 5Ongoing focus on securing necessary hardware from suppliers for TR-3.
  • 62024 delivery numbers are contingent on the actual TR-3 delivery date and customer acceptance.
  • 7Company continues to assess potential impacts on 2024 financials and will provide updates.