8-KMaterial AgreementsExhibits & Filings

Cheniere Energy, Inc. 8-K Report, Material Agreement (May 7, 2015)

Filed May 7, 2015For Securities:LNG

Summary

Cheniere Energy, Inc. (LNG) announced a significant development on May 7, 2015, with the filing of an 8-K report detailing a material definitive agreement. The company's subsidiary, Sabine Pass Liquefaction, LLC, entered into a Lump Sum Turnkey Agreement with Bechtel Oil, Gas and Chemicals, Inc. for the Engineering, Procurement, and Construction (EPC) of the Sabine Pass LNG Stage 3 Liquefaction Facility. This agreement, valued at approximately $2.99 billion, is crucial for expanding Cheniere's liquefied natural gas (LNG) export capacity and represents a substantial investment in its Sabine Pass terminal operations. The Stage 3 facility will include one liquefaction train with a projected production capacity of 4.5 million tonnes per annum (mtpa). The contract with Bechtel encompasses all aspects of the project, from procurement and engineering to construction and commissioning. Key terms include provisions for change orders, performance guarantees, liquidated damages for delays or underperformance, and termination clauses for both parties. Investors should note that the company is continuing to aggressively expand its infrastructure to meet growing global demand for LNG.

Key Highlights

  • 1Cheniere's subsidiary, Sabine Pass Liquefaction, LLC, entered into an EPC contract with Bechtel Oil, Gas and Chemicals, Inc. for the Stage 3 Liquefaction Facility.
  • 2The contract value is approximately $2.99 billion (Contract Price).
  • 3The Stage 3 facility will add one liquefaction train with a capacity of approximately 4.5 million tonnes per annum (mtpa).
  • 4Bechtel Global Energy, Inc. will guarantee Bechtel's obligations under the EPC contract.
  • 5The contract includes provisions for liquidated damages for delays and failure to meet performance guarantees, as well as schedule bonuses for Bechtel.
  • 6Both Cheniere (SPL) and Bechtel have termination rights under specified conditions, including SPL's termination for convenience.
  • 7The agreement demonstrates continued significant investment and expansion in Cheniere's LNG export infrastructure at Sabine Pass.

Frequently Asked Questions

The Stage 3 Liquefaction Facility is a key expansion project for Cheniere, adding significant LNG export capacity. It will increase Cheniere's ability to process and export natural gas as LNG, capitalizing on global demand for this energy source and further solidifying its position as a major LNG exporter.

Bechtel Oil, Gas and Chemicals, Inc. is a major engineering, procurement, and construction company. Under the Lump Sum Turnkey Agreement, Bechtel is responsible for the full scope of work for the Stage 3 liquefaction train, including engineering, procurement, construction, installation, training, commissioning, and placing the facility into service.

The EPC contract has a fixed price of approximately $2.99 billion, subject to adjustments via change orders. Key financial considerations include Bechtel's potential liability for liquidated damages if substantial completion is delayed or performance guarantees are not met, and conversely, Bechtel's entitlement to bonuses for early completion. Cheniere also retains the right to terminate the contract for convenience, with specific compensation terms for Bechtel.

Yes, the contract includes a commencement deadline for construction (June 30, 2015) and a notice to proceed deadline (June 30, 2016). Delays beyond these dates can trigger change orders for Bechtel or allow either party to terminate the contract, potentially impacting project costs and schedules. Bechtel is also incentivized with bonuses for timely completion.