This 8-K filing from Southern Company (SO) on July 10, 2015, primarily concerns updates regarding the Kemper County Integrated Gasification Combined Cycle (IGCC) facility and its rate recovery for Mississippi Power Company, a subsidiary. The filing details Mississippi Power's response to a Mississippi Supreme Court decision mandating the termination of previously implemented rates for the Kemper IGCC, effective July 20, 2015. This requires Mississippi Power to refund approximately $331 million in collected rates (Mirror CWIP) and accrued interest, significantly impacting its financial condition and ability to fund ongoing operations and project completion. In response, Mississippi Power has filed a supplemental notice with the Mississippi Public Service Commission (PSC) proposing an "In-Service Asset Proposal." This proposal aims to recover costs for Kemper IGCC assets that are currently operational and serving customers, such as transmission facilities and combined cycle components. The proposal seeks to implement these as interim rates, effective August 2015, with the goal of not causing additional rate increases for customers beyond what the terminated Mirror CWIP rates would have entailed. The company also anticipates seeking further rate relief for remaining Kemper IGCC assets and notes that if the PSC does not act within 120 days, Mississippi Power may implement temporary rates under bond.

Key Highlights

  • 1Mississippi Power Company must terminate and refund approximately $331 million in previously collected Kemper IGCC rates (Mirror CWIP) due to a Mississippi Supreme Court order, effective July 20, 2015.
  • 2This refund and termination significantly adversely impacts Mississippi Power's financial condition and its ability to secure funds for operations and Kemper IGCC completion.
  • 3A supplemental filing proposes an "In-Service Asset Proposal" to recover costs for operational Kemper IGCC assets, seeking to mitigate further rate increases for customers.
  • 4The In-Service Asset Proposal aims to collect approximately $159 million annually and is requested to be effective for the first billing cycle of August 2015.
  • 5Mississippi Power is requesting these rates as interim, subject to refund, pending a final PSC review.
  • 6If the PSC does not act within 120 days, Mississippi Power may implement temporary rates under bond.
  • 7The company expects to seek additional rate relief for the remaining Kemper IGCC assets.