Summary
Southern Company (SO) filed an 8-K on October 3, 2016, primarily to disclose updates regarding Mississippi Power's Kemper County Integrated Coal Gasification Combined Cycle (IGCC) Project. The filing provides the August 2016 monthly status report to the Mississippi Public Service Commission (PSC). Key information for investors centers on the continued delays and cost overruns associated with the Kemper IGCC project, a first-of-its-kind technology. The report indicates that Mississippi Power expects the Kemper IGCC to be placed in service by November 30, 2016, a delay from previous projections. This revised timeline is attributed to ongoing start-up and commissioning activities, particularly issues with gasifier "B" requiring more inspection and repair time than anticipated. Consequently, the project's cost estimate subject to the $2.88 billion cap has increased by approximately $33 million, reflecting both the extended timeline and specific repairs. The company also provided updated monthly cost estimates for potential further delays, which could add $25 million to $35 million per month in base costs, plus additional costs not subject to the cap like AFUDC.
Key Highlights
- 1Mississippi Power submitted its August 2016 monthly status report for the Kemper IGCC project to the Mississippi PSC.
- 2The Kemper IGCC project's in-service date has been revised to November 30, 2016, due to ongoing start-up and commissioning activities.
- 3Gasifier "B" experienced delays due to extended inspection and repair time for ash removal.
- 4The cost estimate for the Kemper IGCC project, subject to the $2.88 billion cap, has increased by approximately $33 million.
- 5The increase includes $5 million for repairs/modifications to gasifier "B" and $28 million related to the extended in-service date.
- 6Potential further delays beyond November 30, 2016, could incur additional base costs of $25 million to $35 million per month.
- 7Costs not subject to the $2.88 billion cap, such as AFUDC, are also expected to increase with further delays.