8-KRegulation FDOther Events

SOUTHERN CO 8-K Report, Regulation FD Disclosure (Jan 31, 2017)

Filed January 31, 2017For Securities:SOSOJESOJFSOJCSOJDSOMN

Summary

This 8-K filing from Southern Company (SO) on January 31, 2017, primarily provides an update on the Kemper County Integrated Coal Gasification Combined Cycle (IGCC) Project managed by its subsidiary, Mississippi Power. The report details a further delay in the project's in-service date, now anticipated for late February 2017, necessitating a one-week outage for repairs and modifications to ensure sustained operations. This schedule adjustment leads to an approximate $51 million increase in the cost estimate subject to the $2.88 billion cost cap. Furthermore, the filing indicates that updated operating expense projections and lower long-term natural gas forecasts are negatively impacting the project's economic viability analysis. While integrated operation of both gasifiers and combustion turbines has been achieved, the project continues to face challenges in achieving sustained operations. Investors should monitor potential further cost increases, schedule extensions, and the results of the economic viability analysis, as these could materially affect Southern Company's financial performance and regulatory outcomes.

Key Highlights

  • 1Kemper IGCC Project's in-service date delayed again to late February 2017 due to the need for repairs and modifications to ensure sustained operations.
  • 2An approximate $51 million increase in the project's cost estimate, subject to the $2.88 billion cost cap, is reported for December 2016 and projected costs through February 28, 2017.
  • 3Mississippi Power achieved integrated operation of both gasifiers and combustion turbines on January 29, 2017, but identified a need for a one-week outage for further improvements.
  • 4Revised operating expense projections and lower projected long-term natural gas costs are negatively impacting the Kemper IGCC's economic viability analysis.
  • 5Potential for further cost increases and/or in-service date extensions remains due to integration difficulties, system issues, and operational performance challenges.
  • 6Monthly costs for schedule extensions beyond February 28, 2017, are estimated at $25 million to $35 million in base costs, plus additional costs for 'Cost Cap Exceptions' like AFUDC.

Frequently Asked Questions