8-KOther Events

SOUTHERN CO 8-K Report, Corporate Update (Nov 7, 2017)

Filed November 7, 2017For Securities:SOSOJESOJFSOJCSOJDSOMN

Summary

This 8-K filing from Southern Company (SO) addresses significant developments related to the construction of the Plant Vogtle Units 3 and 4 nuclear project. Following Westinghouse's bankruptcy filing and rejection of the original construction agreement, the company has entered into a settlement with Toshiba regarding guarantees and has established new agreements with Bechtel to manage remaining construction activities. These changes are critical for the project's continuation, with updated joint ownership agreements requiring a high threshold (90%) of Vogtle Owner approval for key decisions, especially in the event of adverse circumstances like Toshiba's bankruptcy or significant cost overruns. Investors should note that the filing confirms Georgia Power's recommendation to the Georgia Public Service Commission to continue construction, despite a potential budget increase of over $1 billion or a schedule extension of more than one year, which would trigger heightened approval requirements. The new agreements aim to transition project management to Southern Nuclear and secure Bechtel as the primary contractor, attempting to bring stability to the troubled project. The effectiveness of these new arrangements is contingent on certain approvals, including from the Rural Utilities Service.

Key Highlights

  • 1New agreements are in place with Bechtel to manage remaining construction for Plant Vogtle Units 3 and 4, following Westinghouse's bankruptcy.
  • 2Toshiba has settled with Georgia Power and other Vogtle Owners regarding guarantees related to Westinghouse's obligations.
  • 3Joint ownership agreements have been amended, requiring at least 90% Vogtle Owner approval to continue construction under specific adverse events (e.g., Toshiba bankruptcy, significant cost/schedule increases).
  • 4Georgia Power has filed its 17th Vogtle Construction Monitoring (VCM) report, recommending continued construction of Plant Vogtle Units 3 and 4.
  • 5The company is proceeding with construction despite potential for a budget increase exceeding $1 billion or a schedule extension of over one year, which would trigger higher approval thresholds.
  • 6The effectiveness of the amended Joint Ownership Agreements is subject to approval by the Administrator of the Rural Utilities Service.
  • 7Recourse for Vogtle Owners against Georgia Power or Southern Nuclear for agency performance is limited, except in cases of willful misconduct.

Frequently Asked Questions

The construction is ongoing. New agreements have been put in place with Bechtel to serve as the primary contractor for remaining construction activities, and Southern Nuclear Operating Company will manage the transition from Westinghouse, which filed for bankruptcy. Georgia Power has recommended to the Georgia Public Service Commission that construction continue.

Westinghouse, the original contractor, filed for bankruptcy and rejected the initial agreement. However, a settlement was reached with Toshiba regarding guarantees, and new service and construction management agreements are now in effect to ensure project continuity.

The amended Joint Ownership Agreements require a significant majority vote (at least 90% of ownership interests) from the Vogtle Owners to continue construction if certain adverse events occur. These include Toshiba's bankruptcy or material breach of the settlement, termination of key agreements like the Bechtel Agreement, or if the Georgia PSC deems costs unrecoverable. A budget increase of over $1 billion or a schedule extension of more than one year also triggers this high approval threshold.

Investors should monitor potential cost overruns and schedule delays. The filing indicates a possibility of a budget increase exceeding $1 billion or a schedule extension of over a year, which, while permitted under new agreements, requires higher Vogtle Owner approval. The overall financial viability and recovery of these costs are subject to regulatory approvals and the successful completion of the project.