8-KOther Events

SOUTHERN CO 8-K Report, Corporate Update (Dec 21, 2017)

Filed December 21, 2017For Securities:SOSOJESOJFSOJCSOJDSOMN

Summary

This 8-K filing from Southern Company (SO) provides a critical update on the ongoing construction of the Plant Vogtle Units 3 and 4. On December 21, 2017, the Georgia Public Service Commission (PSC) approved key decisions impacting the project's costs, schedule, and customer recovery mechanisms. Investors should note that the PSC approved the capital costs incurred for the first half of 2017 and confirmed the recommendation to continue construction, with Southern Nuclear Operating Company and Bechtel Power Corporation continuing as key parties. The PSC also approved significant changes that will impact future returns and customer costs. This includes approximately $188 million in customer refunds for 2018, revised in-service dates for Unit 3 (November 2021) and Unit 4 (November 2022), and a revised capital cost forecast for Georgia Power's share of $7.3 billion. Importantly, the PSC clarified that this forecast is not a cost cap, and prudence decisions on cost recovery will be made later. Furthermore, the return on equity (ROE) for calculating the Nuclear Construction Cost Recovery tariff and for allowance for equity funds used during construction will be reduced in stages, impacting future profitability for Georgia Power.

Key Highlights

  • 1Georgia PSC approved $542 million in construction capital costs for Plant Vogtle Units 3 and 4 for the January-June 2017 period.
  • 2The Georgia PSC affirmed the continuation of construction for Plant Vogtle Units 3 and 4.
  • 3Approximately $188 million in customer refunds will be paid by Georgia Power during 2018.
  • 4Revised in-service dates for Unit 3 (November 2021) and Unit 4 (November 2022) were approved.
  • 5Georgia Power's proportionate share of the revised capital cost forecast for Plant Vogtle Units 3 and 4 is $7.3 billion.
  • 6The PSC clarified that the revised cost forecast is not a cost cap, with prudence decisions on cost recovery to be made later.
  • 7The return on equity (ROE) used for nuclear construction cost recovery and allowance for equity funds used during construction will be reduced progressively.

Frequently Asked Questions

This 8-K filing reports on the decisions made by the Georgia Public Service Commission (PSC) on December 21, 2017, regarding the ongoing construction of Plant Vogtle Units 3 and 4. Key approvals included capital costs, continuation of construction, customer refunds, revised project timelines, and adjustments to cost recovery mechanisms.

The Georgia PSC approved approximately $188 million in customer refunds to be paid during 2018. Additionally, while the revised capital cost forecast is not a cost cap, future retail base rates will be adjusted to include carrying costs on prudent capital costs once Unit 3 reaches commercial operation.

The Georgia PSC approved a revised schedule placing Unit 3 in service in November 2021 and Unit 4 in service in November 2022.

The PSC's decision impacts profitability through several measures: the revised capital cost forecast for Georgia Power's share is $7.3 billion, customer refunds totaling $188 million will be issued, and crucially, the return on equity (ROE) used for calculating nuclear construction cost recovery and allowance for equity funds used during construction will be reduced in stages, which will lower the allowed returns during the construction period.