8-KOther Events

SOUTHERN CO 8-K Report, Corporate Update (Mar 19, 2021)

Filed March 19, 2021For Securities:SOSOJESOJFSOJCSOJDSOMN

Summary

Southern Co. (SO) subsidiary Georgia Power Company has announced a delay in the start of hot functional testing for Plant Vogtle Unit 3 into April, attributed to additional construction remediation work primarily concerning electrical installations. While the company is targeting a November 2021 in-service date, a delay is considered likely, potentially adding one month or more to the schedule. Each month of delay beyond November 2021 is estimated to incur approximately $25 million in additional capital costs for Georgia Power. Furthermore, the return on equity used for cost recovery will be reduced by 10 basis points per month after June 1, 2021, if the unit is not yet operational. This news indicates potential cost overruns and extended timelines for the already complex Plant Vogtle project. Investors should monitor the progress of remediation efforts and any further updates on the in-service date and associated costs. The company emphasizes its ongoing commitment to safety and quality, with ongoing reviews of construction quality programs. The ultimate financial and operational impact remains uncertain.

Key Highlights

  • 1Plant Vogtle Unit 3 hot functional testing delayed into April due to additional electrical work.
  • 2Target in-service date of November 2021 is challenged, with a likely delay of one month or more.
  • 3Estimated additional capital costs of $25 million per month for delays beyond November 2021.
  • 4Return on equity for Nuclear Construction Cost Recovery tariff will be reduced by 10 basis points monthly after June 1, 2021, if Unit 3 is not operational.
  • 5Georgia Power is reviewing and improving construction quality programs in response to identified issues.
  • 6Company emphasizes ongoing prioritization of safety and quality in construction and compliance processes.

Frequently Asked Questions