SOUTHERN CO 8-K Report, Corporate Update (Oct 21, 2021)

Filed October 21, 2021For Securities:SOSOJESOJFSOJCSOJDSOMN

Summary

This 8-K filing from Southern Company (SO) primarily announces schedule updates for Georgia Power's Plant Vogtle Units 3 and 4. Unit 3 is now projected to enter service in the third quarter of 2022, and Unit 4 in the second quarter of 2023. These revised dates are attributed to ongoing remediation work, construction productivity challenges, and resource allocation shifts between the units. The company cautions that these new dates are subject to further potential challenges, including construction productivity, the volume of remediation work, system turnovers, and testing progression. Investors should note that additional details regarding cost forecasts, productivity, and resource assumptions related to these schedule extensions will be provided in Georgia Power's upcoming Form 10-Q for the quarter ended September 30, 2021. The filing also includes a cautionary note regarding forward-looking statements, emphasizing the inherent risks and uncertainties associated with these projections, including factors related to construction, regulatory approvals, and potential unforeseen events.

Key Highlights

  • 1Georgia Power has announced revised in-service dates for Plant Vogtle Units 3 and 4.
  • 2Unit 3 is now expected to be operational in Q3 2022, and Unit 4 in Q2 2023.
  • 3Key drivers for the delays include additional remediation work and construction productivity issues.
  • 4The achievability of the new projected in-service dates is subject to ongoing and future challenges.
  • 5Further details on capital cost forecasts and updated assumptions will be disclosed in the upcoming 10-Q filing.
  • 6The company acknowledges the inherent risks and uncertainties associated with these forward-looking statements.
  • 7Potential impacts of the COVID-19 pandemic on construction are reiterated as a factor.

Frequently Asked Questions

Georgia Power now projects an in-service date in the third quarter of 2022 for Unit 3 and in the second quarter of 2023 for Unit 4.

The primary drivers for the schedule changes include the continued identification of additional remediation work, challenges with construction productivity related to electrical installations and remediation, and the subsequent pace of system turnovers. For Unit 4, productivity challenges and resources being diverted to Unit 3 also contributed.

The filing states that Georgia Power expects additional details, including related updates to the total project capital cost forecast for the extension of the in-service dates, to be provided in its Quarterly Report on Form 10-Q for the quarter ended September 30, 2021.

No, the company explicitly states that the achievability of these projected in-service dates is subject to current and future challenges, including construction productivity, the volume of remediation work, system turnovers, and testing progression. Any further delays could result in later in-service dates. The filing also includes a cautionary note about the risks and uncertainties associated with forward-looking statements.