SEMPRA 8-K Report, Regulation FD Disclosure (Jun 23, 2025)

Filed June 23, 2025For Securities:SRESREA

Summary

Sempra (SRE) has filed an 8-K report detailing the enactment of Texas House Bill 5247 (HB 5247), which establishes a new "unified tracker mechanism" (UTM) for qualifying electric utilities. This UTM provides an alternative method for interim rate adjustments related to transmission and distribution (T&D) capital expenditures, streamlining cost recovery for eligible utilities. Oncor Electric Delivery Company LLC (Oncor), in which Sempra holds an 80.25% interest, is expected to qualify for and utilize this new mechanism. The UTM allows qualifying utilities to defer eligible T&D capital investment costs as a regulatory asset and mandates a review period by the Public Utility Commission of Texas (PUCT). Significantly, if the PUCT does not issue a final order within 165 days of filing, the utility can implement temporary rates, with any difference reconciled later. This is expected to improve Oncor's earnings, cash flows, and credit metrics, potentially enhancing earned annual returns on equity by 50 to 100 basis points.

Key Highlights

  • 1Texas enacts HB 5247, creating a "unified tracker mechanism" (UTM) for interim rate adjustments on T&D capital investments.
  • 2Oncor Electric Delivery Company LLC (Oncor), an 80.25% owned subsidiary, expects to qualify for and adopt the UTM.
  • 3The UTM offers an alternative to existing capital tracker filings, designed to reduce regulatory lag.
  • 4Qualifying utilities can defer eligible T&D capital expenditures as a regulatory asset.
  • 5A key provision allows temporary rate implementation if the PUCT review exceeds 165 days.
  • 6Oncor anticipates the UTM will improve its earnings, cash flows, and credit metrics.
  • 7The UTM is projected to enhance Oncor's earned annual returns on equity by approximately 50 to 100 basis points.

Frequently Asked Questions

The unified tracker mechanism (UTM) is a new regulatory framework established by Texas House Bill 5247. It provides an alternative, streamlined process for qualifying electric utilities to apply for interim rate adjustments to recover certain transmission and distribution (T&D) capital expenditures once annually.

Oncor, in which Sempra has an 80.25% stake, is expected to qualify for and use the UTM. This mechanism is anticipated to improve Oncor's earnings, cash flows, and credit metrics. Sempra has affirmed its existing 2025 and 2026 EPS guidance ranges, indicating that the impact of the UTM is expected to fall within these projections.

A utility must operate solely within the ERCOT market, be identified by the PUCT as responsible for transmission infrastructure related to the ERCOT Permian Basin Reliability Plan, and make annual T&D capital expenditures exceeding 300% of annual depreciation.

If the Public Utility Commission of Texas (PUCT) does not issue a final order within 165 days after a UTM filing is submitted, the qualifying utility has the option to implement the requested rates on a temporary basis. Any difference between these temporary rates and the final approved rates would be refunded or credited to customers.