WWD filed 10 annual reports (10-K), 33 quarterly reports (10-Q) and 144 current reports (8-K) between 2016 and 2026.

  1. Deal closed8-K · Jan ’16Jan ’16
  2. Material agreement8-K · Jun ’19Jun ’19
  3. Leadership change8-K · Sep ’21Sep ’21
  4. Leadership change8-K · Aug ’25Aug ’25

Summary

Summary of the 8-K filed September 21, 2026. Cited figures are marked; the original filing is the authoritative source.

Woodward, Inc. (NASDAQ: WWD) filed an 8-K on September 21, 2026 disclosing a plan to transition production out of its Santa Clarita, California, facility.

The Board approved the plan on September 15, 2026. Military fixed-wing and rotorcraft flight control actuation production will move to the company's Spartanburg, South Carolina, aerospace manufacturing campus, which is currently under construction. The company also expects to divest certain legacy commercial rotorcraft, land systems, and business jet product lines primarily produced in Santa Clarita, along with the campus itself.

Those divested product lines will not move to Spartanburg, and the divestiture is expected to close in fiscal year 2027. The company estimates cumulative pre-tax charges of approximately $34 million to $47.5 milliona, consisting primarily of $23 million to $29 million in employee-related severance and benefit costs, $10 million to $16.5 million in anticipated contract termination costs, and $1 million to $2 million in other charges, including asset write-offs, moving costs, and exit-related costs. Nearly all of these charges are expected to be cash expenditures, with only $1 million expected to be non-cash.

Operations at Santa Clarita are expected to cease no later than December 2027, with charges recognized over the transition period and cash expenditures extending through December 2027. According to the accompanying press release (Exhibit 99.1), the decision affects about 400 roles at the facility, with phased transitions. The Spartanburg facility is expected to go online in the summer of 2027 and will also produce Airbus A350 spoiler actuation systems in addition to the transferred product lines.

Key Highlights

  1. Board approved on September 15, 2026 a plan to exit the Santa Clarita, California, facility and consolidate military flight control actuation production in Spartanburg, South Carolina.
  2. Estimated cumulative pre-tax charges of approximately $34 million to $47.5 million, primarily employee-related costs of $23 million to $29 million.
  3. Contract termination costs estimated at $10 million to $16.5 million; other charges of $1 million to $2 million.
  4. Nearly all charges expected to be cash expenditures; only $1 million expected to be non-cash.
  5. About 400 roles at Santa Clarita affected, with phased transitions through the planned move.
  6. Company plans to divest certain legacy commercial rotorcraft, land systems, and business jet product lines along with the Santa Clarita campus, expected to close in fiscal year 2027.
  7. Santa Clarita operations to cease no later than December 2027; Spartanburg expected to go online in summer 2027.

Frequently Asked Questions

  1. What is the total expected cost of the Santa Clarita transition?

    Woodward estimates cumulative pre-tax charges of approximately $34 million to $47.5 million, consisting of $23 million to $29 million in employee-related costs, $10 million to $16.5 million in contract termination costs, and $1 million to $2 million in other charges and costs.

  2. How much of the charges will be paid in cash?

    The company currently estimates that nearly all of the charges will result in future cash expenditures, with only $1 million of the cumulative charges expected to be non-cash.

  3. When will the Santa Clarita facility close and when will the charges be recognized?

    Operations at Santa Clarita are expected to cease no later than December 2027. Charges will be recognized over the transition period as recognition criteria are met, with recognition expected to be substantially completed by December 2027, and cash expenditures extending through December 2027.

  4. What happens to the product lines currently made in Santa Clarita?

    Military fixed-wing and rotorcraft flight control actuation production will move to the Spartanburg, South Carolina campus. Certain legacy commercial rotorcraft, land systems, and business jet product lines will be divested along with the Santa Clarita campus, and these will not be transferred to Spartanburg. The divestiture is expected to close in fiscal year 2027.

  5. How many employees are affected and when will Spartanburg be operational?

    The decision is expected to affect about 400 roles at the Santa Clarita facility, with phased transitions through the planned move. The Spartanburg facility is expected to go online in the summer of 2027 and will also produce Airbus A350 spoiler actuation systems.