8-KOther Events

XCEL ENERGY INC 8-K Report, Corporate Update (Aug 26, 2011)

Filed August 26, 2011For Securities:XELXELLL

Summary

Xcel Energy Inc. (XEL), through its subsidiary Northern States Power Company (NSP-Minnesota), filed an 8-K detailing significant developments in its electric rate cases in Minnesota and North Dakota. In Minnesota, NSP-Minnesota initially sought an approximate $150 million rate increase for 2011, which was later revised. The company received an interim rate increase of $123 million, subject to refund, and has since adjusted its request based on discussions with regulatory bodies like the Department of Energy Resources (DOER) and the Office of Attorney General (OAG). Similarly, in North Dakota, NSP-Minnesota requested an approximately $19.8 million increase for 2011, also revised and approved as an interim rate increase of $17.4 million, subject to refund. The North Dakota Public Service Commission (NDPSC) Staff has recommended a lower increase. Both cases are ongoing, with final decisions expected in late 2011 and early 2012, respectively. Investors should monitor these regulatory proceedings as they will directly impact future revenue and profitability.

Key Highlights

  • 1NSP-Minnesota filed for an electric rate increase in Minnesota, initially requesting $150 million, later revised to $122.8 million after negotiations with regulatory bodies.
  • 2An interim rate increase of $123 million, subject to refund, was approved by the Minnesota Public Utilities Commission (MPUC) effective January 2, 2011.
  • 3NSP-Minnesota filed for an electric rate increase in North Dakota, initially requesting $19.8 million, later revised to $18.0 million.
  • 4An interim rate increase of $17.4 million, subject to refund, was approved by the North Dakota Public Service Commission (NDPSC) effective February 18, 2011.
  • 5The company submitted supplemental testimony in Minnesota, revising its 2011 rate increase request to approximately $122 million and proposing a $29 million increase for 2012.
  • 6These revisions are partly due to project delays, including the Monticello life cycle management/extended power uprate project, impacting expected cost recovery.
  • 7The final decisions for both the Minnesota and North Dakota rate cases are expected in the fourth quarter of 2011 and the first quarter of 2012, respectively.

Frequently Asked Questions