XCEL ENERGY INC 8-K Report, Corporate Update (Aug 30, 2019)

Filed August 30, 2019For Securities:XELXELLL

Summary

Xcel Energy Inc. (XEL) announced significant updates regarding its wind development portfolio on August 30, 2019. Key among these is the petition filed by Northern States Power Company (NSP-Minnesota) to acquire the Mower wind facility. This facility, located in Minnesota, will be repowered and is expected to maintain approximately 99 megawatts (MW) of capacity, aiming to qualify for 100% of the production tax credit upon completion before the end of 2020. The acquisition is anticipated to offer substantial customer financial benefits and aligns with Xcel Energy's clean energy transition goals. Further updates include adjustments to the Crowned Ridge wind projects, where NextEra has reduced the capacity for both build-owner transfer and purchased power agreement components from 300 MW to 200 MW each due to increased transmission costs. These projects are now targeting a November 2020 commercial operation date. Separately, Southwestern Public Service Co. (SPS) has completed the development phase for its Sagamore wind project in New Mexico, a 478 MW project costing approximately $900 million, with construction slated to begin in Q4 2019 and service expected in 2020. These developments underscore Xcel Energy's ongoing commitment to expanding its renewable energy generation.

Key Highlights

  • 1NSP-Minnesota filed to acquire the Mower wind facility (approx. 99 MW) in Minnesota from NextEra Energy, Inc. affiliates, pending regulatory approval.
  • 2The Mower facility will be repowered and is expected to qualify for 100% of the production tax credit upon completion before the end of 2020.
  • 3The Crowned Ridge projects (originally planned at 600 MW total) have been reduced to 200 MW each (300 MW BOT and 300 MW PPA reduced to 200 MW each) due to transmission cost increases.
  • 4The Crowned Ridge projects are now targeting a November 2020 commercial operation date.
  • 5Southwestern Public Service Co. (SPS) has completed the development phase for the Sagamore wind project (478 MW) in New Mexico.
  • 6Sagamore wind project construction is expected to start in Q4 2019 with an estimated cost of $900 million and in-service date in 2020.
  • 7All other announced wind projects have secured necessary permits and interconnections to qualify for production tax credits.