01—Abstract
Summary
Summary of the 8-K filed January 25, 2024. Cited figures are marked; the original filing is the authoritative source.
Eversource Energy (ES) disclosed in this 8-K that its 50/50 joint venture partner Ørsted submitted a revised bid for the Sunrise Wind offshore wind project in New York's latest offshore wind solicitation.
The re-bid proposes up to 924 megawatts of clean energy, with completion expected in 2026. The filing is primarily a project update and does not quantify any financial impact on Eversource's earnings, balance sheet, or capital plan. The most important investor item is a conditional sale agreement.
If Sunrise Wind wins a contract in New York's fourth offshore wind solicitation, Ørsted would acquire Eversource's 50%a stake and become sole owner. Eversource would remain contracted to lead onshore construction. Under the agreement, Ørsted would pay 50% of the negotiated purchase price at closing and the remaining 50% after onshore construction and certain other milestones are achieved.
The purchase price itself is not disclosed in this filing. If the project is not selected, the existing contract would be cancelled under state requirements, and the 50/50 joint venture would remain in place, with both companies assessing their options. The outcome is therefore binary for Eversource.
A win would monetize its offshore wind exposure and convert part of the proceeds into deferred payments tied to construction milestones. A loss would leave the company in the existing joint venture with the contract cancelled and no near-term resolution. Key risks flagged in the forward-looking statements include the bid outcome, the timing and terms of the sale process, the ability to reach definitive agreements, qualification for investment tax credits, and deterioration in offshore wind market conditions.
02—Key points
Key Highlights
- Sunrise Wind, a 50/50 joint venture between Eversource and Ørsted, submitted an updated re-bid in New York's latest offshore wind solicitation, offering up to 924 MW of clean energy.
- If awarded a contract in New York's fourth offshore wind solicitation, Ørsted would acquire Eversource's 50% share and become sole owner of Sunrise Wind.
- Deferred payment structure: Eversource would receive 50% of the negotiated purchase price at closing and the remaining 50% after onshore construction completion and other milestones.
- Eversource would remain contracted to lead the project's onshore construction in a successful re-bid scenario, preserving a construction revenue opportunity.
- If not selected, the existing Sunrise Wind contract is cancelled per state requirements, and the 50/50 joint venture remains in place with options to be assessed.
- The project has reportedly completed state agency design review, secured major supplier and project labor agreements, and expects final federal permits in summer 2026 (per the filing's timing).
- The filing does not disclose the purchase price, the financial impact on Eversource, or the company's accounting treatment of the potential sale.
03—Questions
Frequently Asked Questions
What happens to Eversource's investment in Sunrise Wind if the project wins the New York re-bid?
Ørsted would acquire Eversource's 50% share, making Ørsted the sole owner. Eversource would receive 50% of the negotiated purchase price at closing and the remaining 50% when onshore construction is completed and certain other milestones are met. Eversource would also remain contracted to lead the onshore construction.
What happens if Sunrise Wind is not selected in the New York solicitation?
The existing contract for Sunrise Wind would be cancelled under the state's requirement, but the 50/50 joint venture between Eversource and Ørsted would remain in place. The two companies would then assess their options for the best path forward for the project and its assets. The filing does not describe specific alternatives.
Has Eversource disclosed the sale price or expected financial impact of the potential transaction?
No. The filing states that Ørsted would pay 50% of the negotiated purchase price upon closing and the rest later, but it does not disclose the purchase price, expected gain or loss, or effects on earnings or cash flow.
When is Sunrise Wind expected to be completed, and what is its capacity?
The project is expected to be completed in 2026 and would deliver up to 924 megawatts of clean energy to New York if selected. The company describes it as the most mature offshore wind project in the state's pipeline.
What are the key risks to investors highlighted in the filing?
Key risks include losing the bid to a competing offer, failure to reach definitive sale agreements with the purchaser or with Ørsted, delays or different terms in the sale process, inability to qualify for expected investment tax credits, variability in offshore wind project costs and returns, and deterioration in offshore wind market conditions.