FIRST SOLAR, INC. 8-K Report, Corporate Update (Feb 24, 2017)

Filed February 24, 2017For Securities:FSLR

Summary

This 8-K filing by First Solar, Inc. (FSLR) reports on an initial draw of ¥7.3 billion (approximately $65 million) by its indirect wholly-owned subsidiary, FS Japan Project 12 GK, under a credit facility with Mizuho Bank, Ltd. This facility, totaling up to ¥27.3 billion (approximately $241 million), is specifically for the development and construction of a 59.5 MW photovoltaic power plant in Ishikawa, Japan. For investors, this news signifies ongoing project development and execution in a key international market. The funding secured through this credit facility demonstrates First Solar's ability to access capital for significant projects, which is crucial for its growth strategy and long-term revenue generation. The details of the credit facility, including its structure and repayment terms, provide insight into the financial underpinnings of this specific project and reflect standard practices for project finance in Japan.

Key Highlights

  • 1First Solar's indirect subsidiary, FS Japan Project 12 GK, drew ¥7.3 billion ($65 million) on February 21, 2017.
  • 2The funding is for the development and construction of a 59.5 MW photovoltaic power plant in Ishikawa, Japan.
  • 3The total credit facility available is ¥27.3 billion ($241 million), provided by Mizuho Bank, Ltd.
  • 4The credit facility includes a senior loan, a consumption tax facility, and a letter of credit facility.
  • 5The senior loan bears interest at 6-month TIBOR plus 0.75% and principal repayment begins in April 2019, maturing in October 2036.
  • 6The credit facility is secured by the project's assets and equity interests.
  • 7Customary representations, warranties, covenants, and events of default are included in the agreement.

Frequently Asked Questions

The draw is an initial disbursement from a larger credit facility to fund the development and construction of a 59.5 MW photovoltaic power plant in Ishikawa, Japan, undertaken by First Solar's indirect subsidiary, FS Japan Project 12 GK.

The total credit facility provided by Mizuho Bank, Ltd. for this project is up to ¥27.3 billion, which is approximately $241 million.

The senior loan facility bears interest at a variable rate of 6-month Tokyo Interbank Offered Rate (TIBOR) plus a margin of 0.75%.

Principal repayment on the senior loan facility is scheduled to begin in bi-annual installments from April 30, 2019, with the facility maturing on October 31, 2036.