Skip to content
AnalystLens

International Paper 8-K Report, Exit or Disposal Costs (Feb 13, 2025)

Reports
Financial Events·Exhibits & Filings
Filing Date
Filed February 13, 2025
Period End
February 11, 2025
Securities
IPINPAP
In the record · 2016–202610-K1110-Q328-K153

IP filed 11 annual reports (10-K), 32 quarterly reports (10-Q) and 153 current reports (8-K) between 2016 and 2026.

  1. Material agreement8-K · Dec ’17Dec ’17
  2. Material agreement8-K · Apr ’20Apr ’20
  3. Leadership change8-K · May ’22May ’22
  4. Leadership change8-K · Jul ’26Jul ’26

Summary

Summary of the 8-K filed February 13, 2025. Cited figures are marked; the original filing is the authoritative source.

On February 11, 2025, International Paper Company committed to actions affecting its North American Packaging Solutions business, with estimated aggregate pre-tax charges of approximately $357 milliona.

The largest component is the planned permanent closure of its containerboard mill in Campti, Louisiana, which the Company expects to reduce containerboard capacity by approximately 814,000 tons annualized. The charges comprise a pre-tax noncash asset write-off of approximately $311 millionb, of which $276 million is accelerated depreciation, and pre-tax cash severance and other shutdown charges of approximately $46 million. The Company expects these charges to be recorded in the three months ending March 31, 2025, and the mill closure is expected to reduce its workforce by approximately 481 employees.

A press release issued February 13, 2025 (Exhibit 99.1) broadens the closures to include the Red River containerboard mill in Campti, a recycling plant in Phoenix, Arizona, a box plant in Hazleton, Pennsylvania, and a sheet feeder facility in St. Louis, Missouri. It describes the Red River closure as reducing containerboard capacity by approximately 800,000 tons on an annualized basis, and states that 495 hourly and 179 salaried employees will be affected. The release says all facilities will cease operations by the end of April 2025, while the Form 8-K states that mill manufacturing operations are expected to cease by March 31, 2025.

The Company states it will use attrition, retirements and current vacancies at other locations to minimize employee impact, and that the actions are a step in its transformation into a stronger sustainable packaging solutions company focused on investments that best serve customers. The filing's forward-looking statements caution that the amount and timing of the charges, and the anticipated benefits of the closures, could differ materially from current expectations.

Key Highlights

  1. Estimated aggregate pre-tax charges of approximately $357 million tied to North American Packaging Solutions actions
  2. Approximately $311 million of the charges are noncash asset write-offs, including $276 million of accelerated depreciation; about $46 million are cash severance and shutdown charges
  3. Charges expected to be recorded in the three months ending March 31, 2025
  4. Campti, Louisiana containerboard mill to be permanently closed, reducing containerboard capacity by approximately 814,000 tons annualized (press release states approximately 800,000 tons)
  5. Press release adds closures of a recycling plant in Phoenix, Arizona, a box plant in Hazleton, Pennsylvania, and a sheet feeder facility in St. Louis, Missouri, with all facilities ceasing operations by the end of April 2025
  6. Approximately 481 employees expected to be affected by the mill closure per the 8-K; press release cites 495 hourly and 179 salaried employees affected
  7. Company states it will minimize employee impact through attrition, retirements, vacancies at other locations, outplacement assistance and, where possible, severance

Frequently Asked Questions

  1. What is the total financial impact of these closures?

    The Company estimates aggregate pre-tax charges of approximately $357 million, consisting of about $311 million in noncash asset write-offs (of which $276 million is accelerated depreciation) and about $46 million in pre-tax cash severance and other shutdown charges.

  2. When will the charges be recognized?

    The Company expects the charges to be recorded during the three months ending March 31, 2025.

  3. How much containerboard capacity will be removed?

    The Company expects the Campti mill closure to reduce containerboard capacity by approximately 814,000 tons annualized. The February 13, 2025 press release describes the Red River mill closure as reducing capacity by approximately 800,000 tons on an annualized basis.

  4. When will the facilities stop operating?

    The Form 8-K states that manufacturing operations at the Campti mill are expected to cease by March 31, 2025. The press release states that all listed facilities will cease operations by the end of April 2025.

  5. How will employees be affected?

    The 8-K expects the mill closure to reduce its workforce by approximately 481 employees. The press release states that 495 hourly and 179 salaried employees will be affected across the closures. The Company says it will use attrition, retirements and current vacancies at other locations, and will provide outplacement assistance, mental health support resources and, where possible, severance benefits.