AMERICAN ELECTRIC POWER CO INC 8-K Report, Financial Results (Feb 12, 2026)

Reports
Earnings & Results·Exhibits & Filings
Filing Date
Filed February 12, 2026
Period End
February 12, 2026
Security
AEP
In the record · 2016–202610-K1110-Q328-K138

AEP filed 11 annual reports (10-K), 32 quarterly reports (10-Q) and 138 current reports (8-K) between 2016 and 2026.

  1. Deal closed8-K · Feb ’17Feb ’17
  2. Leadership change8-K · Dec ’20Dec ’20
  3. Leadership change8-K · Mar ’23Mar ’23
  4. Material agreement8-K · Mar ’25Mar ’25

Summary

Summary of the 8-K filed February 12, 2026. Cited figures are marked; the original filing is the authoritative source.

American Electric Power (AEP) reported fourth-quarter 2025 GAAP earnings of $582 milliona, or $1.09 per share, down from $664 million, or $1.25 per share, a year earlier.

Operating (non-GAAP) earnings were $638 millionb, or $1.19 per share, versus $660 million, or $1.24 per share. For full-year 2025, GAAP earnings rose to $3.58 billion ($6.70 per share) from $2.97 billion ($5.60 per share), and operating earnings grew to $3.19 billion ($5.97 per share) from $2.98 billion ($5.62 per share). Revenue for the year increased about 11% to $21.9 billion.

The full-year GAAP gain was driven largely by a $480 millionc after-tax FERC NOLC Order benefit for 2021-2024, which is excluded from operating earnings. AEP Transmission Holdco was the largest single contributor to the GAAP increase. The headline for investors is growth in load and capital needs.

AEP now expects 56 GW of incremental load by 2030, up from 28 GW in October 2025, and says all of it is backed by signed agreements. AEP Texas load alone rose from 13 GW to 36 GW. The company identified $5 billion to $8 billiond of additional transmission and generation investment beyond its $72 billion five-year capital plan, and the investments needed to serve the additional 28 GW are not yet included in either figure.

Management reaffirmed 2026 operating EPS guidance of $6.15 to $6.45 and a long-term operating earnings growth rate of 7% to 9%. The filing also highlights regulatory and affordability dynamics. New rate structures requiring large load customers to pay for grid connection infrastructure were approved in Indiana, Ohio, Kentucky and West Virginia, with similar proposals under review in Michigan, Oklahoma, Virginia and SWEPCO's Texas territory.

Base rate cases were approved or settled in Arkansas, Kentucky, Ohio and West Virginia. Results are preliminary and unaudited, and the press release is furnished under Item 2.02 rather than filed.

Key Highlights

  1. FY2025 GAAP EPS of $6.70 (vs. $5.60 in 2024) and operating EPS of $5.97 (vs. $5.62), a 6% operating EPS increase; the GAAP gain is inflated by a $480M ($0.90/share) FERC NOLC Order benefit excluded from operating results.
  2. Q4 2025 operating EPS of $1.19 vs. $1.24 a year ago, a decline of $0.05, while Q4 GAAP EPS fell $0.16 to $1.09 due to a $52M software impairment and a $4M mark-to-market hedging loss.
  3. Incremental large-load pipeline by 2030 doubled to 56 GW from 28 GW in October 2025, all backed by signed agreements; AEP Texas load rose from 13 GW to 36 GW.
  4. $5B to $8B of additional transmission and generation opportunities identified beyond the $72B 2026–2030 capital plan; the investment to serve the extra 28 GW of load is not yet included.
  5. 2026 operating EPS guidance of $6.15 to $6.45 and 7% to 9% long-term operating earnings growth rate reaffirmed.
  6. Transmission segment (AEP Transmission Holdco) earned $1.16B GAAP in 2025 vs. $790M, though operating earnings rose only $9M, reflecting the FERC NOLC benefit being excluded.
  7. Customer affordability push: large-load tariffs approved in four states and under review in four more; 2.2 GW of generation acquired in 2025 and over 10 GW of gas turbine capacity secured.

Frequently Asked Questions

  1. Why did AEP's GAAP earnings rise so much in 2025 while operating earnings grew more modestly?

    GAAP full-year earnings included a $480 million after-tax benefit from the FERC NOLC Order covering 2021 through 2024, which is excluded from operating earnings. Excluding that and other adjustments, operating earnings rose about 7% to $3.19 billion, or $5.97 per share, versus $5.62 in 2024.

  2. Is AEP on track to meet its 2026 earnings expectations?

    Management reaffirmed 2026 operating EPS guidance of $6.15 to $6.45 and a long-term operating earnings growth rate of 7% to 9%. The company notes it cannot forecast GAAP equivalents, since items such as mark-to-market adjustments, impairments and divestitures may affect reported results.

  3. How much additional capital could AEP deploy beyond its current plan?

    AEP has identified $5 billion to $8 billion of additional transmission and generation projects beyond its $72 billion 2026–2030 capital plan, including competitively awarded 765-kV transmission projects and a planned Wyoming generation facility backed by $2.65 billion of Bloom Energy fuel cell commitments. Investment needed to serve the additional 28 GW of load is excluded from both figures.

  4. Who pays for the infrastructure needed to serve new data center and large-load customers?

    AEP has secured new rate structures in Indiana, Ohio, Kentucky and West Virginia that require large-load customers to pay for the infrastructure needed to connect to the grid, with similar proposals pending in Michigan, Oklahoma, Virginia and SWEPCO's Texas territory. This is intended to protect residential customers from cost increases, though affordability remains a regulatory risk.

  5. What risks should investors weigh from this update?

    Key risks include execution on a rapidly expanding capital program, the timing of Texas load interconnections (dependent on Texas Senate Bill 6 implementation), regulatory outcomes on cost recovery and affordability, and the reliance on signed load agreements converting to actual demand. Q4 results were also pressured by a $52M software impairment, and the press release notes that results are preliminary and unaudited.