Boeing (BA) filed an 8-K on January 23, 2025 to preview preliminary fourth-quarter 2024 results ahead of its full report on January 28.
The company expects Q4 revenue of $15.2 billiona, a GAAP loss per share of ($5.46), and operating cash flow of ($3.5) billion, with cash and marketable securities of $26.3 billion at quarter end. The preview attributes the weakness to the IAM machinists' work stoppage and its settlement, plus charges in Defense, Space & Security and workforce reduction costs announced in 2024. Commercial Airplanes (BOEING's largest segment) absorbs $1.1 billion in pre-tax charges, including $0.9 billion on the 777X tied to higher estimated labor costs under the new IAM agreement, and $0.2 billion on the 767.
Commercial Airplanes expects Q4 revenue of $4.8 billionb and an operating margin of (43.9)%. Management still expects the first 777-9 delivery in 2026. Defense, Space & Security expects $1.7 billion in pre-tax charges on the KC-46A, T-7A, Commercial Crew, VC-25B and MQ-25 programs, with Q4 revenue of $5.4 billion and an operating margin of (41.9)%.
CEO Kelly Ortberg framed the quarter as a stabilization step: the labor agreement is in place, a capital raise was completed to strengthen the balance sheet, and 737, 767 and 777/777X production have restarted. The filing is a preliminary announcement, so the figures may change before the full results are released. Investors should focus on the January 28 report for final numbers, the cash burn trajectory, and the cost of the labor settlement on future margins.
02—Key points
Key Highlights
- Preliminary Q4 2024 revenue of $15.2 billion, GAAP loss per share of ($5.46), and operating cash flow of ($3.5) billion.
- Cash and marketable securities of $26.3 billion at quarter end, following a capital raise to improve the balance sheet.
- Commercial Airplanes recognizes $1.1 billion in pre-tax charges: $0.9 billion on the 777X (higher labor costs from the IAM agreement, incurred over several years) and $0.2 billion on the 767.
- Defense, Space & Security recognizes $1.7 billion in pre-tax charges, led by $0.8 billion on the KC-46A and $0.5 billion on the T-7A.
- Commercial Airplanes expects Q4 revenue of $4.8 billion at a (43.9)% operating margin; Defense, Space & Security expects $5.4 billion at a (41.9)% margin.
- The company still anticipates first 777-9 delivery in 2026 and has restarted 737, 767 and 777/777X production.
- Full Q4 results will be reported January 28, 2025, when final figures and detailed charge impacts will be disclosed.
03—Questions
Frequently Asked Questions
Why is Boeing reporting a large Q4 2024 loss?
The loss reflects the IAM work stoppage and its subsequent agreement, which lowered deliveries and raised labor costs, along with roughly $2.8 billion in pre-tax program charges across Commercial Airplanes and Defense, Space & Security, and costs tied to 2024 workforce reductions.
Is the 777X program still on schedule?
Boeing said it still anticipates first delivery of the 777-9 in 2026, despite a $0.9 billion pre-tax charge reflecting higher estimated labor costs that will be incurred over the next several years.
How strong is Boeing's liquidity after the quarter?
Cash and investments in marketable securities totaled $26.3 billion at year-end 2024, though operating cash flow was negative at ($3.5) billion for the quarter. The company cited a successful capital raise as a step to improve its balance sheet.
Which defense programs are driving the charges?
The $1.7 billion in Defense, Space & Security charges come from the KC-46A ($0.8 billion, tied to manufacturing costs including the IAM work stoppage), the T-7A ($0.5 billion, tied to higher costs on 2026-and-later production lots), and charges on Commercial Crew, VC-25B and MQ-25.
Should investors rely on these figures?
No. The filing is a preliminary announcement issued ahead of the full report on January 28, 2025, so final results and charge amounts may differ. Investors should review the complete Q4 report and the accompanying 10-K when they are released.